EN

ÇÖPLER SULFIDE EXPANSION LEACH PLANT TANK ERECTION


Teknokon performed all tanks, paints and rubber coating of the gold mine sulfide expansion project brought into action by Anagold firm with Amec Foster Wheeler Process Design in İliç town in Erzincan.

Client: GAP
Process Provider: AFW
Location: Erzincan/Turkey
Status: Completed
 

Detailed Scope Of Works

 
Fabrication: Reactors , CS tanks ,SS tanks, Super dublex tanks, Air receiver, tanks, Mixing tanks, Bins
Structural Steel Erection: Platforms ,walkways ,handrails
Equipment İnstallation: Site Erection of Reactors , CS tanks ,SS tanks , Super Dublex Tanks ,Bins, 2500 tons equipment installation
Piping Erection: 50.000 WDI pipe erection
Insulation: Insulation of all piping, tanks and equipment