İSDEMIR AIR SEPARATION PLANT UNIT 8
Teknokon is continuing the installation, construction, mechanics and E&I of the air separation unit 8 supplied by Linde for Isdemir.
Client: Linde Engineering AG
Location: Iskenderun/Turkey
Status: Completed
Detailed Scope Of Works
Civil Works: 8.609 m³ excavation and backfilling, 2.677 m³ concrete foundations
Structural Steel Erection: 193 tons structural steel
Equipment Installation: 1.300 tons of cold boxes, gas tanks and equipments Complete process and utility piping
Piping Erection: 107.157 tons and 2.870 meters of piping
Insulation: 720 m² Piping Insulation
E&I: Distribution panels , 21.300 metres of power&control cabling