META NIKEL - ZORLU GROUP COBALT / NICKEL REFINING FACILITY


The nickel refinery project realized by Zorlu group jointly with Meta company is one of the most comprehensive and biggest projects in mining in Turkey in recent years. Teknokon served as the main construction and mechanics contractor in the Meta Nickel refinery project, undertook the manufacturing and installation of all the site tanks and all piping, building insulation and structural steel installation works, insulation, and scaffolding services, and also served for long for commissioning and maintenance works.

Client: Meta Nikel Kobalt A.Ş.
Process Provider: SNC Lavalin
Location: Manisa / Turkey
Status: Completed
 

Detailed Scope Of Works


Design and Engineering: Tank drawings
Fabrication: 24 pcs carbon steel ,LDX ,Super duplex and Alloyed field Tanks
Civil Works: Excavation and Backfilling ,concrete , tank , equipment, steel structure, pipe rack, miscellaneous foundations
Structural Steel Erection: Fabrication and erection of 3500 tons of steel structure ,pipe rack ,other structures
Equipment Installation: Field Installation of 24 pcs Tanks (Carbon Steel, LDX, Super Duplex and Alloy), Process and utility equipment
Piping Erection: 600 tons Stainless Steel and 400 Tons Carbon Steel piping fabrication and erection
Insulation: Insulation of all piping, tanks and equipment